Shaw Integrated Solutions Turn Key Project Management - How It Works

Prior to ordering:

  1. SIS will establish a PwC Account Number
  2. SIS will partner with PwC's internal or external design team to support the carpet specification process.
  3. SIS & PwC will determine appropriate yardage for a stocking program if required.

Ordering & Project Management Process:

  1. PwC's Architect/PM will send floor covering plans to SIS and request for proposal.
  2. After the receipt of the correct floor plans, project management contact information, detailed scope of work, and site contact from PwC, a site visit will be made within 10 working days by a Shaw Dealer where the project is located. A submittal itemizing the yardage for each product & the cost to install it will be sent to SIS. Floor prep costs are outlined as well. Seaming diagrams will be provided for each project when required.
  3. Proposals will be provided to PwC within 5 business days of receipt of all information required to complete a formal price quote.
  4. PwC will then send a Purchase Order to Cristal Adams at the Strategic Solutions Group.
  5. SIS will order carpet material and communicate production date to PwC.
  6. SIS will schedule material shipment based on PwC's requirements and the material lead time.
  7. SIS will coordinate the delivery of the material with the flooring contractor.
  8. SIS will monitor the installation process as needed.
  9. After reviewing the project and installation, PwC will fill out a Customer Work Release and Acceptance form and forward it to Patrick Hohol.
  10. SIS will generate the invoice for material and services provided to PwC.